Project Description :
The project has a capacity of 35.1 cubic meters per second, including 8 deep wells and related well buildings, about 13 kilometers of water collection pipeline (asbestos cement and steel pipe 250 to 1000 mm), concrete storage tank with a capacity of 24,000 cubic meters, pumping station and The network is distributed.